A concert arena with a capacity of approximately 20,000 people is being built at Munich Airport and is scheduled for completion by 2029. Populous designed the striking structure with its diamond-shaped exoskeleton, while HENN, along with its general planning team, is overseeing the design. But the project, which will cost more than 400 million euros, is far more than just an event venue: with a hotel, mobility infrastructure, and spacious open areas, the goal is to create a new entertainment campus.
A concert hall for 20,000 people is, first and foremost, a logistical challenge. Within just a few hours, thousands of visitors must arrive, move through the building, and then depart again. At the same time, international tour productions require enormous technical capabilities, complex stage setups, and a high-performance power supply.
The Munich Arena, located on the western edge of Munich Airport, aims to integrate these requirements architecturally from the very beginning. Rather than adapting an existing multifunctional hall for concerts, a new venue is being built here whose entire spatial and technical design is geared toward live entertainment.
With the groundbreaking ceremony on October 29, 2026, the construction phase of this privately funded major project has begun. MUNICH ARENA Property GmbH is investing more than 400 million euros in the new campus, which is scheduled for completion in 2029.
Munich Arena: A Facade at the Intersection of Structural Engineering and Media Architecture
The arena’s architectural appearance is defined by an unusual design. An external exoskeleton translates the Bavarian diamond motif into a large-scale geometric structure. It envelops the seven-story hall and gives it a silhouette that is recognizable from afar.
The design is the work of the internationally active architectural firm Populous from London. Further planning is being handled by the master planning team led by HENN Architekten from Munich.
The diamond-shaped structure is more than just a regional landmark. A transparent network of LEDs is integrated into the outer structure, which transforms thebuilding envelope through changing light and media content.
The arena thus becomes an integral part of the event itself. Its impact on the public does not end at the entrance door but begins right in the urban space.



A venue that can hold 20,000 people
Inside, too, the architecture reflects a clear functional design choice. Unlike traditional multipurpose arenas, the Munich Arena is specifically designed for concerts.
The spectator stands rise steeply and encircle the stage in a horseshoe-shaped 270-degree arc. This arrangement is intended to reduce the distance between the audience and the performers and to allow as many seats as possible to have a direct connection to the stage.
The spatial concept thus eschews the neutrality of a universally usable hall. Instead, the specific dramaturgy of a concert serves as the starting point for the design.
This focus on a primary use applies not only to the auditorium but also to the production areas. Short distances, generous technical capacities, and the demands of international tours determine the backstage organization.
In doing so, the architecture must connect two very different worlds: the publicly staged space of the concert experience and the largely invisible infrastructure that makes this experience possible.


100-meter span: The roof as technical infrastructure
Acentral control center: A central control center is a facility that serves as a control hub for various alarm systems in security technology. It receives and processes signals from surveillance equipment and triggers an alarm when necessary. The arena’s roof poses a structural challenge. Steel girders span the interior for approximately 100 meters without supports. The roof area covers about 10,000 square meters.
This span allows for a spectator area free of obstructive columns. At the same time, the structural framework must support considerable additional loads.
An integrated support system is designed to accommodate more than 200 metric tons of lighting, sound, and stage equipment. The roof thus serves not only as a structural element enclosing the space but also as a heavy-duty technical infrastructure.
This flexibility is particularly crucial for international concert productions. Different stage designs, elaborate lighting installations, and large-scale media technology place varying demands on the structure.
As a result, structural engineering becomes an integral part of the usage concept. The technical capabilities of the roof play a key role in determining which events can take place in the arena.
An entertainment campus instead of an isolated arena
With an area of approximately 50,000 square meters, the arena is indeed the centerpiece of the project. However, it is only one component of a larger spatial context.
The campus includes a music hotel, a mobility hub, and park-like outdoor spaces. In addition, there are extensive measures for transportation and media infrastructure.
The various components are not intended to function independently of one another, but rather as a cohesive system.
This presents a major challenge for the project. After all, an arena of this scale requires more than just a functional event space; access, logistics, visitor experience, and operational processes must all be coordinated.
The consulting and project management firm Drees & Sommer is overseeing the subprojects and is responsible, among other things, for construction management and BIM management.
Building InformationModeling (BIM) is being used. BIM stands for Building Information Modeling and refers to the creation and management of three-dimensional computer models that represent a building or facility. BIM is used in the architecture industry to improve the planning, design, and construction of buildings by enabling architects and engineers to create detailed and integrated models…), in which the participating planning disciplines work based on a shared digital building model. Changes to individual building components or technical systems can thus be coordinated with other trades at an early stage.
In a project where the structural system, event technology, energy supply, and transportation infrastructure are closely intertwined, this coordination becomes a crucial prerequisite for implementation.
Energy demand on an industrial scale
The technical aspects of the Munich Arena are particularly evident inits energy requirements, performance, district heating connection, and photovoltaic systems: This trade magazine focuses on the energy consumption of buildings and infrastructure. It examines the various factors that influence energy consumption and the possibilities for reducing it., material use, and the emissions generated by construction and operation.
It will therefore be crucial to determine the actual contribution the planned measures will make during subsequent operation.
The Journey as Part of the Design
An event venue for 20,000 people inevitably generates significant traffic. At Munich Airport, therefore, a multimodal mobility concept is intended to connect the various modes of transportation.
The S-Bahn lines S1 and S8 serve the site via the “Besucherpark” stop. According to project information, the arena is about a 15-minute walk from there. Regional rail connections are also available through the airport, including the ÜFEX.
For motorized traffic, access is provided via the A92 and Freisinger Allee, which is scheduled to be widened to four lanes as part of the project. A new sidewalk and a pedestrian bridge will complete the access infrastructure.
Noteworthy is the planned shared use of existing airport parking lots. About two-thirds of the required parking spaces are to be covered by existing capacity. Only about one-third will need to be newly created.
Whether the mobility concept proves effective in everyday use, however, will also depend on how visitor flows are distributed after events end and how attractive traveling by public transportation actually is.
Between Isar Boulevard and Arena Plaza
Open-space planning is also part of the overarching campus concept.
From the neighboring LabCampus, the so-called Isar Boulevard leads to Arena Plaza. From there, paths wind through the park-like landscape known as “Meadow” to the entrances on the upper level.
Native trees and plants are intended to enhance the quality of the outdoor environment and help create a more pleasant microclimate.
The landscape thus serves multiple functions. It organizes the path network, creates gathering areas, and acts as a bridge between the large-scale event architecture and its surroundings.
Especially for a site that has so far been characterized primarily by airport infrastructure, this raises an interesting urban planning question: Can a primarily functional transportation landscape be transformed into a public gathering place with its own spatial identity?
In any case, the planned open spaces are more than just decorative greenery surrounding an event hall. They are intended to make the campus feel like a cohesive place.
Munich Arena: A New Type of Building at the Airport?
The Munich Arena exemplifies a trend in which large event venues are increasingly conceived as complex infrastructure projects.
The actual hall now constitutes only the visible core of a system comprising mobility,energyEnergy: the ability to perform work or generate heat., media, hospitality, and public open spaces.
Architecturally, the project seeks to give this complexity a distinctive form. The diamond-shaped exoskeleton creates a recognizable external order, while the interior is consistently tailored to the requirements of contemporary concert productions.
A fundamental tension persists: on the one hand, there is the aspiration to create a place that fosters a sense of identity for the region. On the other hand, the arena is located at an airport site characterized by its infrastructure, where public use is likely to be determined primarily by events.
Whether this will actually result in a distinct urban space will not be determined by architecture alone. Equally important will be the quality of the open spaces, accessibility, and the interplay of the various uses.
By the planned opening in 2029, the project must demonstrate how a highly specialized concert venue can be transformed into a spatially and functionally compelling campus.
Project Details
Project: Munich Arena – Live Entertainment Campus
Location: Munich Airport, western airport area
Client: MUNICH ARENA Property GmbH
Architectural Design: Populous, London
General Planning: General planning team led by HENN Architekten, Munich
Project Management, Construction Management, and BIM Management: Drees & Sommer SE
Construction start: October 2026
Planned completion: 2029
Investment volume: more than 400 million euros, privately financed
Arena area: approximately 50,000 m²
Stories: seven
Capacity: up to approximately 20,000 visitors
Roof area: approximately 10,000 m²
Unsupported span: approximately 100 m
Technical roof loads: over 200 metric tons
Energy demand: Power—energy per unit of time generated by a machine or system. and 4 MW of district heating
Target certification: DGNB Gold
Additional uses: Music Hotel, Mobility Hub, Arena Plaza, and park-like outdoor spaces